before 4 years | EMIL EGGER AG

EMIL EGGER heavy lift logistics for ARA Worblental

Precise placement of 3 storage tanks

On behalf of Stiefenhofer AG, Behälterbau, EMIL EGGER was commissioned to transport three storage tanks, each measuring 14.6 x 4.2 x 4.0 m and weighing 28.5 tons, from Bonaduz to Worblaufen to the WORBLENTAL waste water treatment plant and to place them with pinpoint accuracy using two mobile cranes.
emil-egger-worblental-storage-tank-transport-lift-crane-work-heavy-transport
Emil Egger Pneukrank with storage tank

Both access to the site and the space for the assembly of the crane luffing jib were severely restricted. The stroke was also quite tricky due to the tight conditions. Thus, even a fence had to be removed in advance to ensure access for the necessary fleet.

There was a great interaction between the ETE sites in St. Gallen and Avenches for this order. The project managers, dispatch and the drivers all gave full performance.

Many thanks to all involved for the smooth execution and great teamwork.

More news from Emil Egger

emil-egger-crane-work-moving-railway-bridge
111 years old Swiss steamship put to water with EMIL EGGER heavy lift logistics
The ship had to be transported from Ermatingen to Romanshorn by special transport in order to be launched. A bir ordeal, for the spectators and especially for the restorer.
Learn more
Crane assembly EMIL EGGER | Power pole assembly in Pradella - La Punt project
111 years old Swiss steamship put to water with EMIL EGGER heavy lift logistics
The ship had to be transported from Ermatingen to Romanshorn by special transport in order to be launched. A bir ordeal, for the spectators and especially for the restorer.
Learn more
emil-egger-crane-work-moving-railway-bridge
Replacement beaver bridge in Biberbrugg with 1000 tons crane
Numerous onlookers followed the work of replacing the 60-year-old beaver bridge in Biberbrugg from September 30 to October 2. Toneatti AG, together with subcontractors such as EMIL EGGER, carried out the long-planned work. After dismantling the old bridge, the new one, 17 m long and weighing 240 tons, was then set with millimeter precision.
Learn more
Crane assembly EMIL EGGER | Power pole assembly in Pradella - La Punt project
Crane work for power pole assembly
Several cranes from the EMIL EGGER fleet were deployed in the Engadine to ensure smooth assembly: an 80-ton crane, a 100-ton pneu crane and, in some cases, a 250-ton mobile crane with a hook height of over 90 meters.
Learn more
emil-egger-tadano-duebendorf-heavy-lift-logistics-crane-work
All-terrain crane Tadano AC 7.450-1 Operation in Dübendorf
Tadano AC 7.450-1 mobile crane in operation on a high-rise construction site in Dübendorf. Due to the confined space, a compactly built crane with enormous lifting height was required, which can erect construction cranes up to 100 m.
Learn more
default
Derailed railcar put back on tracks thanks to two EGGER cranes
On Sunday, July 17, 2022, a train of the Appenzeller Bahnen derailed in Wasserauen after colliding with a car. To help the railcar back onto the tracks, EMIL EGGER was quickly on the scene with two mobile cranes.
Learn more
emil-egger-pneu-crane-450-tonne-wood-element-view-tower-hardwald-kloten-22
42 m high observation tower was completed in three strokes
The wood used for the construction of the tower comes directly from the hardwood forest. Approximately 310 cubic meters of wood were processed. The whole tower weighs a total of 190 tons. The challenge of stacking the weighty and large prefabricated elements of 42 tons each on top of each other was solved by means of crane work by EMIL EGGER AG. The modules were mounted on top of each other in three lifts up to a height of 42 m by means of a 450-tonne pneumatic crane.
Learn more
emil-egger-emergency-recovery-accident-logistics-train-car-rail-car-help-hotline-6
Complicated recovery operations after train accident
A locomotive collided with a stationary construction train at Zollikofen station (BE) on Thursday, June 2, 2022. The locomotive driver was slightly injured. No other persons were harmed.
Learn more
Swiss steamship launched with EMIL EGGER's heavy-lift logistics.
111 years old Swiss steamship put to water with EMIL EGGER heavy lift logistics
The ship had to be transported from Ermatingen to Romanshorn by special transport in order to be launched. A bir ordeal, for the spectators and especially for the restorer.
Learn more
EMIL EGGER Mini caterpillar crane C6 on the Säntis
When the smallest is suddenly the highest
Today, our smallest mini crawler crane C6 was really big at over 2500 m above sea level. M. on the landmark of eastern Switzerland – the Säntis.
Learn more